Weather Alert

Fairfield Step 2 Sanitary Sewer Project On Schedule For June Completion

The City of Fairfield recently provided an update on the Step 2 sanitary sewer conveyance project, which includes sanitary sewer construction from Lamson Woods, generally following Crow Creek, to MIU. Maxwell Construction has laid the entire portion of sanitary sewer from Lamson Woods to Badget Drive, as one crew continues to work on testing pipe and manholes.

Another crew is expected to arrive in the next few weeks to begin work at the end of Lowe. The work East of Lowe and South of the railroad tracks will take approximately four to six weeks. A third crew will arrive after the first of the year to work on cleaning and televising existing pipe and internally inspect newly installed pipe.

Overall the project is generally on schedule to be completed this coming June.