Fairfield City Engineer Melanie Carlson recently gave an update on the Libertyville Road sanitary sewer project which reported that Drish Construction has completed main installation along both sides of Libertyville Road. They are now working on the alternate “south leg” of the south side, which will be installed behind the houses on the south side of the roadway to serve future development. Grading and clean-up also remain. They project is expected to be completed mid-November with dormant seeding taking place after November 15th.